|

Goodwin Mine Ruling 'Whole New Ballgame'
Federal Court Ruling Reforms Mountaintop Removal Coal Mining

West Virginia was "almost heaven" to John Denver. TLPJ's
federal court victory helps preserve the Mountain State's heritage. |
KEN WARD, JR.
Sunday Gazette-Mail
(WV)
July 18, 2004
Environmentalists are praising a new federal
court ruling that could greatly reform the permitting of mountaintop removal
coal mining.
On July 8, U.S. District Judge Joseph R. Goodwin
ruled that the Army Corps of Engineers could no longer approve mining valley
fills through a streamlined permit process meant only for activities that cause
minor environmental damage.
"It's a whole new ballgame," said Jim
Hecker, a Trial Lawyers for Public Justice attorney who represented the Ohio
Valley Environmental Coalition in the case.
The coalition and two other citizen groups sought
Goodwin's ruling in a federal court lawsuit filed in October.
Another environmental lawyer, Joe Lovett of the
Appalachian Center for the Economy and the Environment, said the corps would now
be able to approve new mining permits only if it conducts more detailed
environmental studies.
Those studies, Lovett said, will show that mining
harms forests and streams and will force companies to reconfigure mining plans
to reduce those impacts.
"The Army Corps of Engineers for too long
ignored its obligation to confront the science that shows that the practice of
mountaintop removal is devastating to the natural environment in West
Virginia," Lovett said.
Reducing paperwork
Before they can open new surface mines, coal
operators must obtain several permits from state and federal regulators. Among
those is a permit from the corps for the actual filling of streams with mining
waste.
In mountaintop removal, coal operators blast off
entire hilltops to uncover valuable, low-sulfur coal seams. Leftover rock and
dirt -- the stuff that used to be the mountains -- is shoved into nearby
valleys, burying streams.
Last year, federal regulators issued a report
that concluded that 1,200 miles of Appalachian streams have been buried or
otherwise "directly impacted" by valley fills between 1992 and 2002.
That 4 1/2-year study found that past, present and future mining in the region
could destroy 1.4 million acres of forest, or 11.5 percent of the study area.
Under Section 404 of the federal Clean Water Act,
the corps can issue two types of permits for filling rivers and streams:
individual permits and general permits.
Individual permits cover specific fill proposals.
Before issuing them, the corps must conduct a "case-by-case
evaluation" of potential environmental effects.
General permits cover categories of activities,
and are issued on a statewide, regional or nationwide basis.
When it issues general permits, the corps spells
out the general conditions that a particular category of activity should meet.
Then, companies seek authorization for specific projects. If they promise to
meet the general conditions, their projects are authorized with much less review
than individual permits.
Congress created the general permit program when
it rewrote the Clean Water Act in 1977, in response to complaints that the
corps' individual permit process was too burdensome and time-consuming for
activities that cause minor environmental impacts.
Environmentalists alleged in their lawsuit that
the agency wrongly approved hundreds of miles of valley fills through a general
permit called Nationwide Permit 21.
In his ruling, Goodwin agreed. The judge threw
out Nationwide Permit 21, and said that the corps must approve valley fills only
through more detailed individual permits.
Goodwin ordered the corps not to approve any new
fills under Nationwide Permit 21.
As of last week, mine operators in West Virginia
had 25 applications for such permits pending with the corps.
At 11 mining operations specifically cited in the
suit, the judge ordered the corps to suspend permits for fills that had not
started as of the July 8 date of his ruling.
Ducks in a row
In Washington, Bush administration officials have
not made a decision about whether to appeal.
"All of that is under review," said
David Hewitt, a spokesman for the corps.
At the corps' district office in Huntington,
agency officials are preparing to begin processing valley fill proposals with
the individual permits that Goodwin said mine operators must now obtain.
Since 1996, only two mining operations -- both
for large mountaintop removal jobs proposed by Arch Coal Inc. to expand its
Samples Mine near Cabin Creek -- obtained individual permits. One of those took
more than three years to be processed. The other took about 1 1/2 years,
according to corps officials.
The corps is reviewing 15 coal company requests
for individual permits.
Mark Taylor, a project manager for the corps'
regulatory branch in Huntington, said it would probably not take the corps much
longer to process individual permits than to review nationwide permits. In large
part, Taylor said, processing time depends on how complete coal company permit
applications are.
"If they have all of their ducks in a row,
and give us all of the information we need up front, we can probably do an 'IP'
faster than we've done some nationwide permits," Taylor said last week.
"There is probably two or three months more
processing time involved," he said. "All things being the same, it
would be at least 60 days and maybe six months longer."
Disruptions to permitting
In legal briefs filed with Goodwin, coal industry
lawyer Bob McLusky argued that the suit against the corps was "the third
attempt by environmental organizations to halt coal mining in Central
Appalachia."
The late U.S. District Judge Charles H. Haden II
had issued two major rulings that would have restricted mountaintop removal.
Both were overturned by the 4th U.S. Circuit Court of Appeals in Richmond, Va.
"Although the first two attempts proved
ultimately unsuccessful, the coal industry still struggles to recover from the
substantial disruptions to the permitting process caused by the
litigation," McLusky wrote.
McLusky cited an April report by the U.S.
Department of Energy that showed coal production in Southern West Virginia,
Eastern Kentucky and Ohio remains more than 20 percent below production in 1997,
the year before the first round of mountaintop removal litigation.
"The legacy of past lawsuits that had
temporarily halted the issuance of permits needed to open new mines continued to
constrain the amount of coal produced," the DOE report said.
The DOE report also blamed several other factors
for the production decline.
"Bankruptcies continued to plague Appalachia
as another mid-sized coal company filed for Chapter 11 in early 2003, while
several other coal companies were still working through their bankruptcy
processes," the DOE report said.
"Geological problems and underground mine
fires added to the decline in coal production in some Appalachian states,"
the report said. "Finally, several mines closed as they reached the end of
their reserve base adding to the continuing reserve depletion that is affecting
coal production in the East.
"Declining productivity and increasing labor
costs also contributed to lower production levels in the region."
In their briefs, industry lawyers cited testimony
from two coal company officials who complained that obtaining individual permits
would take too long and cost too much.
John McDaniel, an Arch Coal engineer, said in an
affidavit that the lawsuit specifically targeted three of his company's permits.
If Arch Coal needs to obtain new, individual
permits, McDaniel said, it would take company officials four to six weeks just
to prepare permit applications. Then, he said, it could take the corps six
months to review the applications.
In a separate affidavit, Danny Cox of Massey
Energy said that it typically takes three months to obtain a nationwide permit
from the corps. Obtaining an individual permit would take nine to 12 months, Cox
said.
McLusky concluded that a ruling in the
environmental groups' favor "will greatly lengthen the permit process for
new mines and will disrupt planned and ongoing operations."
After Goodwin's ruling, West Virginia Coal
Association President Bill Raney said his group wasn't yet sure what the effect
would be. Raney said the industry is "hopeful that it's all going to work
out."
"There are a number of members that are
going through the [individual permit] process," Raney said. "Their
opinion is that perhaps it's a more efficient process than it had a reputation
for."
Significant impacts?
Before it can issue an individual Clean Water Act
permit, the corps must do a preliminary study of the potential impacts of the
mining proposal involved.
If the corps determines that the effects of the
proposal will not be significant, then it can issue the permit. But if the
agency determines that the effects are significant, then it must do a much more
detailed Environmental Impact Statement, or EIS, that can take more than a year.
So far, the corps has only required such a study
for one mining proposal -- Arch Coal's proposed Spruce Mine near Blair in Logan
County, which was the subject of the initial mountaintop removal lawsuit in
1998. That study, begun after Haden blocked the corps' first permit for the
mine, has never been completed.
Corps officials say they don't expect to order
coal companies to perform an EIS for each mining permit application.
Ginger Mullins, chief of permitting for the
corps' Huntington branch, said the biggest difference between nationwide and
individual permits is that individual permits involve a more open public review
process.
In processing nationwide permit authorizations
for mining proposals, the corps actually performed a brief site-specific review
that was a sort of hybrid between general and individual permits.
But in doing so, Goodwin ruled, the agency evaded
the public notice and comment that is required for individual permits.
Now, the corps will have to issue public notices
for all mining permits, allow public comments and, in some cases, hold public
hearings.
"This ruling gives people the opportunity to
comment on these permits, which result in such devastation to their lives and
communities," said Vivian Stockman, project coordinator for the Ohio Valley
Environmental Coalition.
By opening the process, Goodwin's ruling will
allow environmental groups to challenge the corps if the agency issues an
individual permit without first demanding a detailed EIS.
"They've never done the scientific studies
to support issuing these permits," said Hecker, one of the environmental
group lawyers. "The cumulative impacts of all of these fills are
significant."
To contact staff writer Ken Ward Jr., use
e-mail or call (304) 348-1702.
|